Change Control, Impediments & Issues

PMP Certification Prep
0% Complete
Question 1/7
Single AnswerAct

On a predictive school-construction project, the principal asks the site foreman directly to move a wall to enlarge a classroom. The foreman asks the PM whether to start tomorrow. What should the project manager do?