Change Control, Impediments & Issues
PMP Certification Prep
0% Complete
Question 1/7
Single Answer
Act
On a predictive school-construction project, the principal asks the site foreman directly to move a wall to enlarge a classroom. The foreman asks the PM whether to start tomorrow. What should the project manager do?
Ask the principal to submit a change request, analyze its impact with the team, and take it to the CCB before any work starts
Move the wall and record the change at the end of the phase
Reject the request because the design is baselined
Tell the foreman to proceed because the principal is a key stakeholder