EVM Formula Drills
PMP Certification Prep
0% Complete
Question 1/5
Single Answer
Analyze
A project has BAC = $200K, EV = $80K, AC = $100K. Using the typical EAC formula (assuming past performance continues), what is the Estimate at Completion?
$250K
$220K
$240K
$180K
Submit Answer