Governance, Escalation & the PMO
PMP Certification Prep
0% Complete
Question 1/6
Single Answer
Act
On a predictive highway-resurfacing project, the cost management plan lets the PM absorb variances up to 5% of a control account. A materials price spike will push one control account 9% over. What should the project manager do?
Wait until month-end reporting to see whether prices fall
Analyze the variance and options, then escalate to the sponsor through the defined path because the threshold is exceeded
Reduce the pavement specification to stay within budget
Absorb the overrun quietly using contingency from unrelated work packages