Question 1/25
Single Answer
Analyze
A predictive network has three paths: A-B-E = 14 days, A-C-E = 17 days, and A-D-E = 12 days. Activity C is delayed by 2 days. What is the effect on the project end date?
The end date moves by 1 day
No effect, because path A-B-E has float
The end date moves by 5 days
The end date moves by 2 days, because C is on the critical path (A-C-E)