Final Practice Set 3

PMP Certification Prep
00:000% Complete
Question 1/25
Single AnswerAnalyze

A predictive network has three paths: A-B-E = 14 days, A-C-E = 17 days, and A-D-E = 12 days. Activity C is delayed by 2 days. What is the effect on the project end date?