Change Control, Impediments & IssuesBE3 Change
Change Control Across Approaches (BE3)
Same goal everywhere: understand impact, decide at the right level, update and communicate
| Step | Predictive | Agile | Hybrid |
|---|---|---|---|
| Capture | Formal change request in the change log | New backlog item or story | Backlog item; change request if it touches a contract or release baseline |
| Assess | Impact on scope, schedule, cost, quality, risk | PO and team assess value and size | Both, depending on level |
| Decide | CCB or PM within delegated authority | Product Owner reprioritizes | PO inside the release; CCB for baseline or contract |
| Implement & update | Update baselines and plans, then execute | Pull into a future sprint | Update release plan and baselines as needed |
| Communicate | Change status to stakeholders per the comms plan | Visible on the backlog and in reviews | Both channels |
No Unapproved Changes, No Gold Plating
Whatever the approach, nobody adds work on their own. Predictive changes go through change control; agile changes go through the Product Owner. Size is never an exemption: a “small” change still gets assessed.